




 |

SanderSon Bay Fine Homes presents the schedule of tasks and projects below. Dates are best guesses as various tasks rely opon inspections, permits, materials, etc. which are beyond our control. We will continue to update this schedule as we know of changes.
Contact us if you have questions or concerns about this schedule.
| UPCOMING Task / Project Description |
Estimated Date |
| House Approaching Close, Closing Date Set |
To Be Determined |
Upcoming Tasks listed above are estimated dates.
Actual dates may vary and we will update these as we become aware of schedule changes. |
| COMPLETED Task / Project Description |
Completion Date |
| Cabinets & Ceramic Tile Completed |
November 23, 2007 |
| Drywall & Stucco Completed |
October 8, 2007 |
| Windows In, ALL Trades Inspection Scheduled |
August 14, 2007 |
| Slab Poured |
May 30, 2007 |
| Completed Tasks listed above are dated when photographed. |

|